Partial IP outage
Scheduled on 12/03/2026 02:09:00 Status Finished Estimated finish 12/03/2026 02:30:00We are currently exoeriencing a partial outage effectng a small number of IP ranges, We are investigsting and wil update this notification soon.
Related servers / services
UPS B Maintenance Notification – Battery Upgrade & Resilience Improvement
Scheduled on 10/03/2026 10:00:00 Status In-Progress Estimated finish 12/03/2026 16:00:00Following our previous communications regarding the investigation into the B Feed UPS behaviour during recent brownout events, we are now proceeding with the planned resilience upgrade to the UPS B battery system.
As previously advised, our investigation concluded that the most probable contributing factor to the UPS response during the voltage disturbance was degradation within the existing battery string. To address this and improve system resilience, we will be upgrading UPS B to operate with dual battery strings.
Upgrade Overview
We have now received the required battery systems, consisting of two full battery strings (80 batteries in total). The remaining upgrade components are confirmed to be arriving on Monday, enabling us to proceed with the planned installation.
Once complete, UPS B will operate with:
• Two battery strings (80 batteries total)
• Increased redundancy within the battery system
• Improved resilience during supply disturbances
Maintenance Window
The upgrade works are scheduled as follows:
Date: Tuesday 10th March
Start Time: 10:00
Estimated Duration: Up to 6 hours
During this maintenance period, UPS B will be taken offline in order to complete the upgrade works.
Operational Impact
During the works:
• Circuit B will remain connected to mains power but will not have UPS battery protection.
• In the unlikely event of a grid power disturbance during this window, equipment connected solely to the B Feed may experience interruption.
• Circuit A will remain fully operational and protected by UPS at all times.
While no issues are expected during the works, the B Feed should be considered “at risk” for the duration of the maintenance window.
Customer Guidance
Customers operating single-powered equipment connected to the B Feed should consider their equipment at risk during the maintenance period.
If you are unsure whether your equipment is connected to the B Feed, please respond to this notification and we will be happy to confirm your current power configuration.
Engineering Works
Our engineering team will carry out the works on-site, and a UPS specialist engineer will be on hand throughout the maintenance window. The work will be completed as efficiently as possible in order to minimise the period during which the B Feed is without battery protection.
We appreciate your continued patience while we implement this upgrade, which will strengthen the resilience and redundancy of the B Feed UPS system.
If you have any questions or would like to discuss mitigation options, please do not hesitate to contact us.
Kind regards,
NOC Team
Blynx AIM Ltd
Related servers / services
Planned Network Maintenance — 7th & 8th March 2026
Scheduled on 07/03/2026 12:00:00 Status Completed Maintenance Estimated finish 08/03/2026 11:30:00We are writing to inform you of planned network maintenance at our Saxon House data centre facility on the weekend of 7th and 8th March 2026.
What is happening?
We are decommissioning our legacy Juniper routing infrastructure as part of an ongoing programme to modernise and improve the resilience of our core network. During this work, obsolete equipment will be removed from the network, and any services still carried by the legacy platform will be migrated to our new infrastructure.
When?
Maintenance window: Saturday 7th March – Sunday 8th March 2026
Risk window: Saturday 7th March, 20:00 – Sunday 8th March, 08:00
What to expect
No service interruption is expected within the data centre during this maintenance window. However, all network services should be considered at risk for the duration of the risk window.
Customers with connectivity to our Telehouse location should be aware that there may be a brief interruption during the cutover to the new platform. The data centre itself is expected to continue operating normally throughout.
All efforts will be made to keep any disruption to an absolute minimum.
Do I need to do anything?
No action is required on your part. We recommend that you make your technical teams aware of the maintenance window as a precaution.
Contact
If you have any questions or concerns, please reply to this notification or contact our operations team on 01242 234567.
We appreciate your patience and understanding as we continue to invest in the reliability and performance of our network.
Kind regards,
Blynx AIM Limited
Data Centre Operations — Cheltenham