UPDATED 21:45: At Risk Notification – B Feed UPS Fault Rectification Works

Scheduled on 08/04/2025 13:00:00 Status In-Progress Estimated finish 10/04/2025 13:00:00

Update at 13:00 BST 10/04/2025

Engineers discovered that a battery was reading a lower voltage compared to the rest of the system. The affected battery was replaced, and the system was charged for 24 hours. Subsequently, a test was conducted to verify the battery system’s ability to support the UPS. The test was successful, and the circuit was restored, ensuring that all systems are now protected from power interuptions.

We understand that no one was impacted by this maintenance. Thank you for your patience.

Kind Regards,
Blynx AIM NOC Team



Updated at 21:45 BST 08/04/2025

Engineers have identified the component suspected of causing the malfunction in our B power feed. Consequently, the replacement will not be available until tomorrow afternoon.

As a precautionary measure, we are placing the system into bypass mode. This action will have minimal impact to the majority of customers with dual AB power, particularly those out of business hours.

The scheduled work is set for 22:30 BST and is essential for repairing, testing on a load bank, and reintroducing the UPS into the circuit once its functionality is confirmed.

Thank you for your patience during these maintenance works.

Kindest Regards,
Blynx AIM NOC Team



As of 13:00 BST 08/04/2025

Dear clients,

Please be advised that emergency maintenance works are being carried
out to rectify a fault on the B Feed UPS system within our data centre
at Saxon House, Cheltenham.

During this maintenance window, the B feed will be considered at
risk. The A feed remains fully operational, and all critical
infrastructure continues to be supported via the redundant power path.



Scope of Works:
• Investigation and repair of the identified fault on B Feed UPS
• Testing and validation of restored UPS functionality



Impact:
• The B Feed UPS will be considered at risk until the fault is
resolved.

Important Notes for Customers:
• If your equipment is single-fed and connected to the B feed, your
service should be considered at risk during this time.
• If you have single power feed equipment and are unsure which
power feed you are connected to, please contact us by raising a ticket
to [email protected] for confirmation and advice.



Risk Mitigation Measures:
• A Feed UPS and backup systems remain operational and fully
monitored
• On-site technical staff and engineers are present throughout
• All works follow our standard change management and risk
mitigation procedures



We appreciate your understanding while we carry out these necessary
works to maintain the resilience and reliability of our facility.

Kindest Regards,
Blynx AIM NOC Team

Related servers / services

All servers and services at Saxon House in Cheltenham.